Detailed guide on obtaining municipal approval for grid-tied solar PV installations in South Africa.
Municipal approval is a mandatory step before connecting a solar PV system to the municipal grid. Each municipality has specific application processes and requirements under NERSA, NRS 097-2-1, and SANS 10142-1. Non-approval = illegal operation, insurance void, and potential disconnection.
Submit a complete package — missing docs = instant rejection.
Follow this 4-step timeline — use your SAPVIA installer to avoid delays.
Installer prepares full package + site survey.
Hand-deliver or email to electrical dept.
Engineer checks SLD, CoC, NRCS compliance.
On-site visit → final CoC → grid connection.
An inspector will review wiring, safety, and metering compliance. Only after approval may the system be switched on.
Following municipal procedures ensures legal compliance and smooth grid connection. Start 30 days early, use SAPVIA installers, and submit complete paperwork — your system stays safe, insured, and export-ready.